ALL PROJECTS AS OF June 16, 2021

Project Type Lead Agency Status Current Status (% 
​Complete)
Next Milestone Next Milestone (Target Date)

ROADWAYS

         
Patton Chapel Road Improvement - Modifies two existing intersections into one, in front of Gwin Elementary School. Extends sidewalk along Patton Chapel Rd.  For additional information on this project, contact Jefferson County Roads
​and Transportation at (205) 325-5141. (See More Info.)
Jefferson County Construction   Completion of Roadway Improvements
Fall 2021
Valleydale Rd Widening (Little) - Widens Valleydale Rd from Riverchase Pkwy to Business Center Drive
ALDOT Design 95% ROW Acquisition ROW Acquisition To Start 2021
Valleydale Rd Widening (Big) - Widens Valleydale Rd to five lanes from Caldwell Mill Rd to Hwy 280. ALDOT ROW Acquisition
​94 Total tracts
​6 Pending​
87% Utility Relocation   2021
South Shades Crest Rd, Additional Northbound Lane - Adds a northbound lane on South Shades Crest Road from Willow Lakes Drive to Hwy 150.                Jefferson County      Permitting Process 95% Final Design & Right of Way Acquisition Fall 2021
Galleria Blvd Extension - County led project that extends Galleria Blvd by Chick-Fil-A to Old Montgomery Highway Jefferson County Purchasing Right of Way 50% Construction 2023
Highway 150 Right Turn Lane @ Whisperwood Lane City of Hoover Bid Process 1% Construction Fall 2021
Tamassee Lane Roadway and Drainage Improvements City of Hoover Design Stage 50% Construction August 2021

SIDEWALKS,GREENWAYS & TRAILS

         
Chapel Rd Sidewalks - Extend sidewalk from Matzek Drive to Park Ave.  (See more info.) ALDOT Utility Coordination
​ 
50% Construction Fall 2021
US Hwy 150 Sidewalk - Provides sidewalk on one side of Hwy 150 from Hwy 31 to Cahaba River Estates. ALDOT Design & Planning  85% Right of Way  Acquisition TBD
Alford Avenue Sidewalks - Phase 1 - Constructs sidewalks along Alford Avenue from Haden Street to Pine Lane and Haden Street from Alford Avenue to Blue Ridge Blvd. City of Hoover Final Design Stages 95% Right of Way Acquisition Fall 2021
Inverness Community Greenway - Constructs sidewalk and trail along Inverness Parkway from Valleydale Rd, through the City's Inverness Nature Park. ALDOT Construction
30% Completion Fall 2021

GENERAL / MISC

.
         
Marywood Drainage Project City of Hoover Bid Process 1% Construction Fall 2021
Bluff Park Pavilion City of Hoover Design 5% Construction Winter 2021
US Hwy 31 Street Light Replacement, Phase 2 - Installs new street lighting along Hwy 31 from Patton Chapel Rd to I-65. ALDOT Design

100% Final Plans Submitted To ALDOT For Bidding 
August 2021
Inverness WWTP Filter Rehab
​ Repairs Existing Filters
City of Hoover Construction 91% Completion July 2021
Upgrade Pump Station Telemetry - Inverness & Riverchase Pump Stations City of Hoover Bid Process 1% Construction/Implementation Fall 2021
Upgrade Woodford Pump Station City of Hoover Pump Station Redesign & Bid Process 5% Construction/Implementation Winter 2022